Final wind turbine installed just ahead of lockdown

- Advertisment -

Perdekraal East Wind Farm announced the installation of its 48th wind turbine, two weeks ahead of schedule, on 24 March 2020. The final lifting was a celebratory moment for the largely South African crew, who have since left the construction site, in compliance with the COVID-19 regulations, which came into effect just three days after this milestone.

“Whilst operational wind farms are classified as essential services, being part of the country’s electricity production, supply and maintenance category, the ongoing construction of Perdekraal East Wind Farm has, of necessity, temporarily ceased operations”, said Glenn Hobson, the construction project manager for Perdekraal East Wind Farm.

The dedicated turbine installation crew began the erection of the first of its 48 wind turbines on this Western Cape mega-wind farm project, at the end of August last year. The crew worked hard to take advantage of the periods of low wind to install all the turbines, completing this operation thirteen days ahead of schedule.

“We expected to only complete this major milestone on 6 April, so considering the current pandemic, the early completion is an unexpected blessing as we hadn’t anticipated the full impact of the COVID-19 virus,” added Hobson.

The wind turbines stand 115 m tall to allow for optimum energy production, however, when one of the blades stand vertically, the turbine’s tip height is 168 m high. The three 53,2 m blades, made from fibreglass reinforced epoxy, are connected to the rotor at ground level before being lifted to the top of the turbine tower. The heaviest component is the nacelle, which contains the generator and gearbox; and weighs 86 tonnes.

“I am continually impressed by the results that the wind turbine generation lifting teams produce, often under difficult circumstances and within tight deadlines, requiring innovative approaches to the completion of tasks. The pride that the local teams take in their work is truly inspiring and I cannot complement their work ethic highly enough. It has truly been a pleasure working with this team,” concluded Hobson.

LEAVE A REPLY

Please enter your comment!
Please enter your name here

Latest Articles

Free webinar: The rise of battery storage solutions

The Rise Of Battery Storage Solutions Why and how the impact of global lockdowns is driving this boom Tuesday, 26 May, 10am (GMT+2) The globe has slowed...

Industrial UPS for major local petrochemical company

When a major petrochemical producer in Mpumalanga required an industrial UPS solution, the PowerLine DPA 20-120 kVA modular three-phase UPS system from ABB was...

Essentials to meet South Africa’s electricity needs

by Alexander Jan Ham (Pr.Eng.), Eskom (retired) While the government’s draft Integrated Resource Plan (IRP2019) is very thorough and makes impressive reading, it lacks decisiveness...

AI might help Eskom function more optimally

South Africa presents itself as the perfect candidate for the Xpress Optimization as it has had an ongoing energy crisis leading to loadshedding, dating...

Sharpening SA’s supply chain

As South Africa's industry returns to work in line with the precautionary measures and phased integration prescribed in Level 4 of the current Covid-19...

New employee to support telecoms industry

DEHN Africa, a surge and lightning protection specialist company, has appointed Raymond Koekemoer as a business development manager to serve the telecoms industry. Koekemoer...

Free webinar: Developing your energy vision: Securing finance for your organisation

The sixth webinar in the Power & Electricity World Africa webinar series is taking place live tomorrow, 19 May at 10h00 (GMT+2). With only 500...

High-efficiency solar cell from standard equipment

Trina Solar announces that its State Key Laboratory (SKL) of PV Science and Technology (PVST) has fabricated a PERC cell with 23,39% efficiency solely...

Partnering to respond to Covid-19 pandemic

Cummins has reached an agreement with 3M to manufacture high-efficiency particulate filters for use in 3M’s Powered Air Purifying Respirators (PAPRs). PAPRs are important...

Creating certainty: Reliable power in complex times

by John Lewis, Agrekko As the world moves towards a new future, a new normal as defined by the coronavirus and its implications, there is...

For safe electrical panel inspection

The use of IR windows for safe electrical panel inspection is becoming more common place. Some electrical panel manufacturers now pre-fit their panels with...

Compact IR thermometers for spot measurement or thermal images

Instrotech, the local representative of Optris, a manufacturer of non-contact temperature measurement devices, has launched CTratio which offers many improved parameters and new features....

Essential maintenance during lockdown

Rope-access specialist Skyriders has received CIPC certification to operate as an essential services provider during the ongoing lockdown. This has enabled it to continue...

Medupi Unit 3 finally reaches full generating capacity

Eskom has announced that Medupi’s Unit 3 has reached the full generation capacity of 793 MW. This follows a 75-day outage to repair major...

Engineers in lockdown: What are you doing?

Many engineers are at home under forced lockdown regulations. But what are they doing? Here's an opportunity to tell us and possibly win a...
- Advertisement -