Energize Electricity regulations on new generation capacity amended
- Advertisment -

Electricity regulations on new generation capacity amended

- Advertisment -

Information from Webber Wentzel  –

On 16 October 2020, the minister of Mineral Resources and Energy, Gwede Mantashe, gazetted amendments to the Electricity Regulations on New Generation Capacity, 2011, in terms of the Electricity Regulation Act, 2006, providing scope for municipalities to develop their own power generation projects, subject to certain requirements.

The official media statement issued by the Department of Mineral Resources and Energy on the gazetted amendments can be accessed here.

The purpose of the regulations is, among other things, to facilitate planning for the establishment of new generation capacity. The amendments thus clarify the regime applicable to municipalities in so far as the determinations which may be made by the minister under section 34 of the Act are concerned.

Key amendments

The regulations have been limited in application, providing that only organs of state active in the energy sector may procure new generation capacity. Such procurement now includes base load, mid-merit load, peak load, new generation capacity, and energy storage.

Municipalities, as organs of state, are now eligible to apply to the minister for the procurement or purchase of new generation capacity in accordance with the Integrated Resource Plan.

A municipality will need to conduct and submit a feasibility study where it intends to deliver the new generation capacity project through an internal mechanism as contemplated in section 76(a) of the Municipal Systems Act.

It must also submit proof that it has complied with the provisions of section 120 of the Municipal Finance Management Act and the Municipal Public-Private Partnership Regulations, where it intends to deliver the new generation capacity project through an external mechanism as contemplated in section 76(b) of the Municipal of the Municipal Systems Act.

Furthermore, it must submit proof that the application is aligned with its Integrated Development Plan.

Lastly, the conclusion of power purchase agreements between buyers or procurers and IPPs will be further subject to any approvals required in terms of the Municipal Finance Management Act or the Municipal Systems Act, together with the Public Finance Management Act, as the case may be.

Contact Alexandra Felekis, Webber Wentzel, Tel 011 530-5625, alexandra.felekis@webberwentzel.com

LEAVE A REPLY

Please enter your comment!
Please enter your name here

Latest Articles

Electricity regulations on new generation capacity amended

Information from Webber Wentzel  - On 16 October 2020, the minister of Mineral Resources and Energy, Gwede Mantashe, gazetted amendments to the Electricity Regulations on New...

All-in-one testing for motors

Megger has combined all the functions frequently required for testing electric motors in a unique and innovative handheld instrument, the MTR105 static motor analyser....

Municipality seeks independence from Eskom’s expensive power

eThekwini Municipality is intent on reducing its reliance on Eskom by generating its own power and buying from independent power producers (IPPs). According to a...

Multi-plug adaptors pose a danger to consumers

Information from the South African Bureau of Standards  -   The increased use of devices and appliances has resulted in the increased use of multi-plug adaptors...

Now you can “see” sound and locate the invisible threat

Fluke’s new ii910 Precision Acoustic Imager detects corona, partial discharge and gas, steam and compressed air leaks which can hurt both production uptime and...

Massive improvement in replacement hours at major mining company

Cummins Filtration has supported one of South Africa’s largest mining companies in undergoing a comprehensive trial study to extend the service intervals for automotive...

Multi-channel approach improves remote employee, customer experiences

by Dharshan Naidoo, Infobip Africa As the Covid-19 pandemic irrevocably redefined the way we communicate and work, remote working and mobile workforces have become central...

Bokamoso Solar Park helps meet demand, reducing risk of load shedding

The 78 MW Bokamoso Solar Park situated near Leeudoringstad in the North West Province, has reached full grid code compliance, commenced commercial operations, and...

Independent transmission system “essential” to end load shedding

by Roger Lilley, Now Media  -   To overcome the scourge of load shedding, two components are urgently needed: more generating capacity and an improved and...

Drivers improving the business case for solar power

Information from IM Power  -   Covid-19 has presented businesses with the opportunity to re-evaluate both their operational models and costs. Proactive organisations found themselves navigating...

Temperature monitor and controller saves municipality money

Instrotech recently supplied its DPM4003 and DPM3001M (low- and high-alarm relay output) temperature indicators to Levivi22 Engineering and Projects, the company contracted by Tshwane...

Undertaking wall thickness testing at Tutuka

During the lockdown in June, rope-access specialist Skyriders undertook an inspection of pulverised fuel (PF) piping at Tutuka power station near Standerton in Mpumalanga...

Rentable solar power now available

Aggreko, a leading provider of mobile, modular power, temperature control and energy services, today announces the immediate availability of its solar power rental offer....

EU solar power association signs cooperation agreement with SAPVIA

SolarPower Europe and the South African Photovoltaic Industry Association (SAPVIA) have signed a Memorandum of Understanding (MoU) to strengthen cooperation and explore new business...

First BW4 wind farm celebrates commencement of commercial operations

South Africa’s first bid window four (BW4) wind farm, part of government’s Renewable Energy Independent Power Producer Procurement Programme (REIPPPP), has announced its Commercial...
- Advertisement -